| The piling rig angled for raking piles. |
|
| Twenty-eight driven pre-cast concrete piles prior to excavation/ cutting back and the connection into the pile cap. |
|
| The cutting back of the piles in preparation for construction of the pile cap. |
|
| Pile cap prior to casting concrete. |
|
| Reinforcement cage for the pile cap foundation. |
|
| Turbine foundation (pile cap) awaiting installation of the tower insert. |
|
| 650 tonne crawler crane installing the lower section of the tower. |
|
| Nacelle and hub of the Vestas V90, 1.8MW turbine, its approximate weight of 80 tonnes. The unit will be lifted 85m on to the turbine tower. |
|
| 650 tonne crawler crane lifting the nacelle and hub on to turbine tower. |
|
| 45 metre long blade for the Vestas V90 turbine on road transport. Its approximate weight is 6.5 tonnes. |
|
| Installations of the cables. |
|
| General view over North Pickenham wind farm. |
|