Twenty-eight driven pre-cast concrete piles prior to excavation/ cutting back and the connection into the pile cap.
The cutting back of the piles in preparation for construction of the pile cap.
Pile cap prior to casting concrete.
Reinforcement cage for the pile cap foundation.
Turbine foundation (pile cap) awaiting installation of the tower insert.
650 tonne crawler crane installing the lower section of the tower.
Nacelle and hub of the Vestas V90, 1.8MW turbine, its approximate weight of 80 tonnes. The unit will be lifted 85m on to the turbine tower.
650 tonne crawler crane lifting the nacelle and hub on to turbine tower.
45 metre long blade for the Vestas V90 turbine on road transport. Its approximate weight is 6.5 tonnes.
Installations of the cables.
General view over North Pickenham wind farm.